Our Sites

In March 2017, Zenobe Energy acquired its first 3.85MW across five battery sites co-located with solar parks. This was followed by the completion of our 9.6MW Kings Barn site in West Sussex in August - at the time the largest dynamic frequency response battery unit in the UK.

Our two largest sites - the 29MW site at Aylesford in Kent and the 20MW site at Claredown in Essex –started operation in February 2018. Construction of these sites was completed in record time and at reduced cost thanks to new ways of working with our suppliers. We have further projects planned for later in 2018.